Decking Company Tacoma
In this article
  1. The ledger, and the rim joist behind it
  2. Posts, footings and beams
  3. Guards and stairs
  4. The slider, the siding and everything else on that wall
  5. What’s underneath: the lower-level patio
  6. Permits, and whether to repair or replace
  7. What to ask before you sign
  8. Common questions about split-level deck replacement
  9. Get a free on-site estimate for your split-level deck
  10. About the author

By Danu “Daniel” Rotari, owner of Decks Restore. Washington contractor license CC DECKSRL797P2. Updated November 9, 2026.

Tacoma and the Pierce County suburbs around it have plenty of split-level and split-entry houses from the 1960s and ’70s. Many of them have the same kind of deck: it comes off a slider in the kitchen or dining room, sits anywhere from a half story to a full story above the yard depending on the slope, and the lower level opens out underneath it. When one of those decks needs replacing, the biggest surprises are usually in the house. How the original builder tied the deck to the wall, what the rim joist looks like behind it, and what else is mounted on that wall all decide the scope and the price.

These decks also predate almost every rule we build to now. According to the American Wood Council, the residential code didn’t spell out how a deck ledger should be fastened to a house until its 2009 edition. Since then it has required half-inch bolts or lag screws into the house’s band joist. A deck from 1974 was built decades before any of that. If you’re comparing builders for a replacement like this, start with how we handle deck replacements around Tacoma.

The ledger, and the rim joist behind it

The ledger is the board that holds the deck to the house. On a split-level it’s fastened to the main floor’s rim joist, the board that sits on top of the lower-level wall. That rim joist is holding up your house as well as your deck, and it’s exactly where water from a badly attached ledger ends up.

On a deck from this era, check how the ledger is fastened. Nails were common. Today it has to be bolts or lag screws, and the American Wood Council notes that decks held on by nails have collapsed with as few as one or two people on them. Look for flashing too, and check whether the ledger was bolted straight over the siding. Current practice, per the AWC’s prescriptive deck guide, is to remove the siding where the ledger goes and install corrosion-resistant flashing. The AWC also has a plain-language article on why a nailed-on ledger can pull away from the house.

I’ve walked onto decks that looked fine from the street and found the house’s rim joist behind the ledger soft enough to push a screwdriver into. We’ve written about how ledger rot spreads into the house. On a split-level the inside face of that rim joist is often hidden behind a finished lower-level ceiling, so some damage can’t be seen until the old ledger comes off. A good quote says up front how rim joist repair will be handled and priced if it turns up.

Some houses can’t take a ledger at all. The AWC guide notes that some older homes have band boards less than an inch thick, too thin to support a deck. It also prohibits attaching a ledger to brick, stone or masonry veneer, to a floor that cantilevers out past the wall below, or to a bay window. If your split-level has brick on the lower level or a main floor that overhangs the wall underneath, the new deck will probably need to be freestanding, carried on its own beam and posts along the house.

Posts, footings and beams

Three things I see on old elevated decks make a rebuild the honest answer. One is 4×4 posts running more than eight feet. Another is posts notched halfway through to take a beam, which was common practice decades ago and leaves very little wood where the load is highest. The third is posts sitting on surface blocks instead of poured footings.

The AWC’s prescriptive guide sets 6×6 as the minimum post size, and we use 6×6 posts on anything more than 30 inches off the ground. A split-level deck is usually well past that. Footings are their own question in Tacoma’s wet clay. We compared helical piles with poured concrete for that soil, including when the extra cost of piles is worth it.

Then check the beam, joists and hangers against current span tables. Roofing nails in joist hangers are common, and they’re the wrong fastener. A deck eight or ten feet up also needs lateral resistance that a low deck never asks for. The residential code’s first deck-specific lateral connection detail, two 1,500-pound hold-downs tying the deck joists back to the house framing, appeared in the 2009 edition. Freestanding decks at that height usually need bracing instead.

Guards and stairs

On decks I’ve torn out, the railing was in worse shape than the decking about seventy percent of the time. Railings from the 1970s often fail today’s rules as well. Washington’s residential code requires guards at least 36 inches high where the deck is more than 30 inches above grade, with no opening large enough for a 4-inch sphere to pass through. Older codes allowed much wider gaps. If you’re choosing new railings, here’s how cable, glass and picket railings hold up over ten years in this climate.

Stairs are the other thing that fails inspections. Riser heights have to be consistent from top to bottom, and old deck stairs often aren’t. A full-story deck needs a long stair run, and sometimes a landing, which is a small deck of its own with footings and guards. People who think of the job as “a deck plus some steps” are often surprised by how much of the budget the stairs take.

The slider, the siding and everything else on that wall

The slider is where water most wants to get into the house. The residential code lets the deck surface sit up to 7¾ inches below the top of the threshold as long as the door doesn’t swing out over the deck, and a step down keeps rain from driving under the door. The step-down also matters when laying out a deck for a view, because it lowers the railing in your sightline from inside. If the slider is the original, consider replacing it at the same time. Its sill flashing and the new ledger flashing meet at the same spot, and doing both at once means opening that wall only once.

Look at what else is mounted in the ledger zone. Dryer vents, hose bibs, outdoor outlets and porch lights often sit right where the new ledger and flashing need to go, and they may have to move. Moving an outlet or a light can also trigger a separate electrical permit.

Taking the siding off at the ledger raises another question on these houses. Homes built before 1978 may have lead-based paint. Under the federal renovation rules, which the Washington State Department of Commerce runs here, work that disturbs more than 20 square feet of painted exterior surface on a pre-1978 home has to be done by a lead-safe certified firm, unless testing shows the paint is lead-free. Ask whoever you hire whether they’re certified.

Then there’s the old lumber. Residential use of CCA, the arsenic-based wood treatment, ended on December 31, 2003, so pressure-treated framing on a 1970s deck was probably treated with it. Don’t burn it, and dispose of it according to local rules.

What’s underneath: the lower-level patio

On a split-level, the space under the deck is usually a patio outside the lower-level door, and every rain drips straight through the gaps in the decking onto it. If you want that space dry, the time to decide is before the new decking goes on, because the better systems are installed above the joists. There are two basic designs, and we’ve explained why the below-joist kind tends to rot.

Plan beam placement around the lower door and windows as well. A dropped beam that’s fine on paper can end up at head height right outside the basement slider. If you think you’ll want a cover over the deck later, decide that now too. A cover on an elevated deck puts more load into posts and footings, and it’s much cheaper to plan for than to retrofit. We go through the post and guardrail conflicts that come with covering an existing upper deck.

Permits, and whether to repair or replace

A deck attached to the house or more than 30 inches above grade needs a building permit in Tacoma, so a split-level walkout deck replacement is always permitted work. Taller decks and sloped lots sometimes need engineering, and the city decides when. We’ve written up what Tacoma asks for on a deck permit, and we pull the permit and schedule the inspections on our jobs.

Whether to repair or replace comes down to the structure. If the ledger is nailed, the posts are notched 4x4s on surface blocks and the guards fail current rules, resurfacing would just put new boards on a frame that won’t pass. We’ve laid out the three questions we ask about every old deck, and you can check your current deck for warning signs before anyone comes out.

What to ask before you sign

  • How will you check the rim joist, and how will repair be priced if it’s rotted?
  • Will the new deck attach to the house with a ledger or stand on its own, and why?
  • What post size and footing type are you planning?
  • Will the siding come off at the ledger, and who patches it afterward?
  • My house was built before 1978. Is your firm lead-safe certified?
  • What happens to the slider, dryer vent and outlets on that wall?
  • What does your workmanship warranty cover on the new ledger connection? It helps to know what a workmanship warranty should spell out.

We’ve also put together the questions every deck builder should be able to answer, whatever the job.

Common questions about split-level deck replacement

Can a new deck attach to my split-level’s rim joist?

Usually, if the rim joist is solid and thick enough and the siding comes off so the ledger can be bolted and flashed. Ledgers can’t go on brick or stone veneer, cantilevered floors or bay windows, and some older homes have band boards too thin to carry a deck. In those cases the deck is built freestanding.

Do I need a permit to replace a deck on a split-level in Tacoma?

Yes. The deck is attached to the house and almost always more than 30 inches above grade, and either one triggers a building permit in Tacoma.

Can I keep the old posts and footings?

Rarely on a deck this old. Posts that are 4×4, notched to take the beam, or set on surface blocks are the usual reason a replacement turns into a full rebuild. Footings have to be checked for size and depth before anything new goes on them.

Why do old deck replacements cost more than people expect?

The extra cost usually comes from the house wall and the stairs. Rim joist repair, siding removal and patching, moving vents and outlets, and a long stair run with a landing all show up on split-level jobs, and none of them are visible from the yard.

Get a free on-site estimate for your split-level deck

I do every estimate myself, at your property, and on an older deck that means getting underneath it to look at the ledger, posts and footings before giving you a number. Call Daniel at (253) 677-0290 or book a free estimate online, and browse photos of decks we’ve finished. We build across Tacoma, from Northeast Tacoma and the North End to South Tacoma, and in nearby cities like Puyallup, Gig Harbor, Federal Way and Bonney Lake. You’ll find pricing, recent projects and reviews on our page about deck replacement and new builds in Tacoma.

Decks Restore LLC
748 Market St #173, Tacoma, WA 98402
(253) 677-0290
Monday to Friday, 9 a.m. to 5 p.m. Saturday, 9 a.m. to 2 p.m. Closed Sunday.
WA contractor license CC DECKSRL797P2

About the author

Danu Rotari, known to most customers as Daniel, owns Decks Restore and has built decks across Tacoma, Pierce County and the South Sound for more than a decade. He quotes every project himself, walks active job sites, and signs off on the work before final payment. His specialties are composite decks, pool deck resurfacing and elevated builds that need engineering. Washington contractor license CC DECKSRL797P2.

Share this article

Thinking about a project like this?

Decks Restore is locally owned and operated in Federal Way, WA. Tell us about your deck and we'll schedule a free on-site estimate.

Request A Free Quote Call (253) 677-0290